Progress continues at the CO2 terminal in Esbjerg

Project news

19/12/2025

Progress continues at the CO₂ terminal in Esbjerg.

Construction work is advancing steadily at the Greensand CO₂ terminal. Most recently, stair towers and platforms have been installed to provide safe access to the top of the storage tanks and allow routing for pipes, cables, and the CO₂ condenser.

At the same time, paving of the truck station access area is now complete, and preparations are underway to establish a construction site for the next contractor handling mechanical installations.

With concrete works completed and the site handed over in clean and safe condition, we are moving forward - step by step - towards EU’s first full-scale offshore CO₂ storage site.